Time consumed in product development
is the biggest issue. Approvals and bulk fabric in house consumes approx. 75%
of the total pre-production activity time and as far the most time consuming
task. Whole supply chain needs a system which
•
Reduces time spent in PD.
•
Co-ordinates
internally for all pre -production activity each.
•
Producing a high quality clear cut
specifications for manufacturing and quality purposes
About 60% of the delays are at Pre
production stage and remaining at the production stage and reduction of such
time can help the company in meeting the delivery dates on time. Controlling
the delay would enable the company to reduce the deviation from the
schedules lead time and honor the delivery date.
STEPS IN PROJECT PLANNING
•
Order Identification
•
Activity Differentiation
•
Activity sequencing
•
Activity Duration estimation
•
Critical Path
•
Gantt Chart
•
PERT Chart
•
Analysis of activities
SCOPE OF CRITICAL PATH METHOD
•
Garment merchandising activities are
characterized by people oriented function .
•
Interdependent activities are
synchronized between succeeding and preceding activities to make process
network .
•
Critical chain is the solution the
garment industry is looking for as it is based on task dependency.
CRITICAL PATH METHOD
•
The Critical Path Method,
abbreviated CPM, or Critical Path Analysis, is a mathematically
based algorithm for scheduling a set of project activities. It is an important
tool for effective project management.
•
It was developed in the 1950s by the
US Navy when trying to better organize the building of submarines and later,
especially, when building nuclear submarines. Today, it is commonly used with
all forms of projects, including construction, software development, research
projects, and product development, engineering, and plant maintenance, among
others. Any project with interdependent activities can apply this method of
scheduling.
•
The essential technique for using
CPM is to construct a model of the project that includes the following:
- A list of all activities required to complete the project (also known as Work breakdown structure),
- The time (duration) that each activity will take to completion, and
- The dependencies between the activities.
OUT PUT
•
The shortest time possible to
complete the project.
•
The longest path of planned
activities to the end of the project.
•
The earliest and latest that each
activity can start and finish without making the project longer.
•
Which activities are
"critical" (i.e., on the longest path) and which have "total
float" (i.e., can be delayed without making the project longer.
PROCESSES INVOLVED IN APPAREL
MERCHANDISING
Activity Identification
PRE PRODUCTION ACTIVITIES
•
Garment shrinkage test sample
•
FIT Sample
•
AD Sample
•
Wash sample
•
Garment processing test sample
•
Yellow tag sample
•
Green tag sample
•
Fabric shade band
•
Fabric Processing test
•
Size set
Production activities
•
Garment shade band
•
Production pull
•
TOP Sample
•
Final inspection
Activity sequencing according to the
requirement of the order
1.Order
Confirmation
|
2.Garment
spec sheet (GSS) & Wash Standard receiving
|
3.BOM
Recd.
|
4.SBD-Po
Receipt By
|
5.Sampling
yardages booked
|
6.S/Ydg.
In-house By
|
7.Bulk
Fabric Booking
|
8.Fabric
Process test report from buyer
|
9.Fit
Submit
|
10.Fit
approval
|
11.Wash
Sample submission
|
12.Wash
Approval
|
13.Garment
Processing test sample submission(GPT)
|
14.Yellow
tag sample submission(YTS)
|
15.Yellow
tag approval
|
16.Receiving
of fabric bits from supplier
|
17.Fabric
Shade band submission
|
18.Fabric
shade band approval
|
19.GTS
Submit On (Green tag sample)
|
20.GTS
Comments/Approval Or Sealed
|
21.Fabric
In house
|
22.Trims
Ordered On
|
23.Trims
In house By
|
24.GPT
Report receiving
|
25.Size
Set ready and approval
|
26.PPM(Pre
Production meeting)
|
27.PCD(Production)
|
28.Garment
shade band submission
|
29.Garment
Shade Band Approval
|
30.Production
Pull Submission
|
31.Production
pull approval
|
32.TOP
Submission (Top of the production)
|
33.TOP
approval
|
34.Final
Inspection
|
35.X-Factory
|
36.X-india
|
Sequencing of activities and
application of critical path method
•
Activity sequencing chart
•
GANTT Chart
•
PERT Chart - to elaborate but
powerful tool
Time Taken
In Critical & Non Critical Activities
Critical
Activities
|
Planned
Duration
|
Floats
|
Order
Confirmation
|
1day
|
0
|
Size
Breakdown receiving from the buyer
|
8 days
|
0
|
Bulk
Fabric booking
|
1 day
|
0
|
Fabric
In House
|
35 days
|
0
|
Size set
ready and approval
|
3 days
|
0
|
PPM
|
1 day
|
0
|
PCD(Cutting)
|
1 day
|
0
|
Garment
shade band submission
|
4 days
|
0
|
Garment
shade band approval
|
4 days
|
0
|
Production
Pull Submission
|
4 days
|
0
|
Production
Pull approval
|
2 days
|
0
|
TOP
Submission
|
6 days
|
0
|
TOP
approval
|
4 days
|
0
|
Final
Inspection
|
1 day
|
0
|
X
factory
|
1 day
|
0
|
X India
|
7 days
|
0
|
Non
critical Activities
|
Planned
|
Float as
per CPM
|
GSS and
wash standard receiving
|
1 day
|
3 days
|
BOM
receiving
|
1 day
|
3 days
|
Sampling
Yardages booked
|
1 day
|
3 days
|
Sampling
Yardages In house
|
2 days
|
3 days
|
FPT
Report receiving from the supplier
|
15 days
|
20 days
|
FIT
submission
|
7 days
|
8 days
|
FIT
Approval
|
10 days
|
8 days
|
Wash
Sample Submission
|
10 days
|
3 days
|
Wash
sample approval
|
10 days
|
3 days
|
GPT
Submission
|
7 days
|
18 days
|
YTS
Submission
|
10 days
|
8 days
|
YTS
approval
|
8 days
|
8 days
|
Receiving
of fabric bits from the supplier
|
7 days
|
17 days
|
Fabric
Shade band submission
|
11 days
|
9 days
|
Fabric
shade band approval
|
3 days
|
9 days
|
Green
tag submission
|
10 days
|
3 days
|
Green
tag sample approval
|
7 days
|
3 days
|
Trims
ordered on
|
1 day
|
10 days
|
Trims in
house
|
32 days
|
10 days
|
GPT Report
receiving
|
15 days
|
18 days
|
EFFECT OF POOR MPP
IMPROPER PRODUCTION PLANNING
General Reasons of delay
in pre-production activities
•
sampling yardages
•
Order of trims and fabric
•
sampling threads
•
wash standard achievement
•
GTS sample
•
Internal Miscommunication
•
Concept of two buying houses
•
Load in sampling and R&D Washing
•
Late delivery of sampling trims and
sampling yardages
•
Difference between the lot of fabric
used in development stage and sampling stage
•
Improper handling
•
Time of Issuing & stores
•
Holidays & leaves
•
Delay from buyer side in sending the
standard and sample
•
FPT Report
•
GPT report
General Reasons of delay in
Production Activities
•
Improper Documentation
•
Start up loss
•
Delay in Fabric/Trims becoming
in house
•
Delay in approval of Garment shade
band(as it was seen in many styles)
•
Improper checking of trims at the
time of in house
•
Delay in approval/Review of
Production Pull
•
Improper quality checking
•
TOP rejection or delay in approval
of TOP
•
Improper presentation of TOP
Merchant’s priority and critical
path method
•
While estimating tasks hidden safety
should not be taken into account for each task .In the case of Arvind
following are the tasks where hidden safety should not be taken:-
- Ø FIT Sample approval
- Ø Wash Sample approval
- Ø Production Pull submission(specially in the case of small order quantities)
- Ø TOP Submission.
- Ø Wash sample submission
.
•
Early finishes should be promoted
rather than completion on time .
- Ø No due dates for individual tasks but finish as early as possible and hand over , next person for next task. In the case of issuing a Sampling indent a merchant generally does not issue it to the sampling by the time sampling Yardages comes in house. In most of the cases it kills time as sampling yardages comes late .Merchant should issue Sampling indent as soon as the order is confirmed, so that they can focus on another task.
•
Lapses in the information
Communication
- Ø . In these cases Merchant should communicate directly face to face with the concerned person and formalities can be done in later stages. As Arvind works on Oracle data base , so it creates such kind of problem.
•
System related problem should also
be removed , these problems pertain to the delay which are caused due to excess
time taken in documentation, interdepartmental Communication, the release of
orders, flow of work, process followed etc.
•
Planning of Pre production
activities
•
Resubmission
•
Improve resource scheduling to
reduce bottle necks and improve efficiency.
- Ø Mostly in the case of resubmission, before the sample goes into the sampling every item should be in stock
•
Un availability of sampling yardages
at the time of re submission
•
Actual thread and Wash sample.
•
Item issue delay from the store
•
Identification of Opportunities to
change sequential tasks into parallel activities by understanding the true
predecessor and relationships among activities.
•
Creation of proper Mechanism
for communication
- Ø Speak clearly
- Ø Write clearly
- Ø Repeat the things
- Ø Get feed back from the respondent
•
Criticality of wash
•
Fabric/Trims In house Problem
•
Imported and Local items
•
Approval Problem
•
Internal and external Tracking
down mechanism of samples
•
Proper co ordination among the team