বৃহস্পতিবার, ১৩ সেপ্টেম্বর, ২০১২

Critical path of merchandising



Time consumed in product development is the biggest issue. Approvals and bulk fabric in house consumes approx. 75% of the total pre-production activity time and as far the most time consuming task. Whole supply chain needs a system which
       Reduces time spent in PD.
       Co-ordinates   internally   for all    pre -production activity each.
       Producing a high quality clear cut specifications for manufacturing and quality purposes
About 60% of the delays are at Pre production stage and remaining at the production stage and reduction of such time can help the company in meeting the delivery dates on time. Controlling the delay would enable the company to reduce the deviation   from the schedules lead time and honor the delivery date.
STEPS IN PROJECT PLANNING
       Order  Identification
       Activity Differentiation
       Activity sequencing
       Activity Duration estimation
       Critical Path
       Gantt Chart
       PERT Chart
       Analysis of activities
SCOPE OF CRITICAL PATH METHOD
       Garment merchandising activities are characterized by people oriented function .
       Interdependent activities are synchronized between succeeding and preceding activities to make process network .
       Critical chain is the solution the garment industry is looking for as it is based on task dependency.
CRITICAL PATH METHOD
       The Critical Path Method, abbreviated CPM, or Critical Path Analysis, is a mathematically based algorithm for scheduling a set of project activities. It is an important tool for effective project management.
       It was developed in the 1950s by the US Navy when trying to better organize the building of submarines and later, especially, when building nuclear submarines. Today, it is commonly used with all forms of projects, including construction, software development, research projects, and product development, engineering, and plant maintenance, among others. Any project with interdependent activities can apply this method of scheduling.
       The essential technique for using CPM is to construct a model of the project that includes the following:
  1. A list of all activities required to complete the project (also known as Work breakdown structure),
  2. The time (duration) that each activity will take to completion, and
  3. The dependencies between the activities.
OUT PUT
       The shortest time possible to complete the project.
       The longest path of planned activities to the end of the project.
       The earliest and latest that each activity can start and finish without making the project longer.
       Which activities are "critical" (i.e., on the longest path) and which have "total float" (i.e., can be delayed without making the project longer.
PROCESSES INVOLVED IN APPAREL MERCHANDISING

Description: https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEgfopIzW3Kh90WCo7blpchO98Jj0IGYpGc6WgfJTwLufymRbm8SwqCSUknDKIr0v6Et3tE-gP-5uv5BH1GKJjD7xq7TYk6HPRCM-eEar1r9ZR7SVG3P_Q0Nv_ZLBDuhe3TXaa3arWTFWx_1/s320/a.jpg

Activity Identification
Description: https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEh8ueY7SarHgV1QdizGubpYDwj1tdFpjd0y5dlxWTb8bb4hMp6ComGN8pRQt-5p6yxJPwC6LK0iaVUVjU-CcY-MD3MmQAZPKCHeBr6dpW41Uwz-L2tMeUCrF-jjvaxrujB3sXfQk44CcqQB/s320/b.jpg

PRE PRODUCTION ACTIVITIES
       Garment shrinkage test sample
       FIT Sample
       AD Sample
       Wash sample
       Garment processing test sample
       Yellow tag sample
       Green tag sample
       Fabric shade band
       Fabric Processing test
       Size set
Production activities
       Garment shade band
       Production pull
       TOP Sample
       Final inspection
Activity sequencing according to the requirement of the order
1.Order Confirmation
2.Garment spec sheet (GSS) & Wash Standard receiving
3.BOM Recd.
4.SBD-Po Receipt By
5.Sampling yardages booked
6.S/Ydg. In-house By
 7.Bulk Fabric Booking
8.Fabric Process test report from buyer
9.Fit Submit
10.Fit approval
11.Wash Sample submission
12.Wash Approval
13.Garment Processing test sample submission(GPT)
14.Yellow tag sample submission(YTS)
15.Yellow tag approval
16.Receiving of fabric bits from supplier
17.Fabric Shade band submission
18.Fabric shade band approval
19.GTS Submit On (Green tag sample)
20.GTS Comments/Approval Or Sealed
21.Fabric In house
22.Trims Ordered On
23.Trims In house By
24.GPT Report receiving
25.Size Set ready and approval
26.PPM(Pre Production meeting)
27.PCD(Production)
28.Garment shade band submission
29.Garment Shade Band Approval
30.Production Pull  Submission
31.Production pull approval
32.TOP Submission (Top of the production)
33.TOP approval
34.Final Inspection
35.X-Factory
  36.X-india

Sequencing of activities and application of critical path method
       Activity sequencing chart
Description: https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEi_IW-XOh3niK9oEFrraFZ6gq9j0q3yeCw-dIlJX6kK1h4qP-rufuR4yR6LXXiv9ykTGURHyIsAz877sgoaAYBb2mAHKJgO5A61fI_QMW7h2dtEfHuo8zntyTW2o_zD4gJe5tgozoe6ae3c/s320/g.jpg

Description: https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEipNEuu3F18FvQFrAiBS6pkhLE_MolXDSbup4nc1iWgbzQ6BUzQtbtltekT4h64z2AvvbuZ6p0FeKRaeBrO882n4N0rouHCYtIa36kJyiGWOrCt1pJzOwHgHQ2g_Nuhab0_mExl-r2-VYZt/s320/h.jpg

       GANTT Chart
Description: https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEi82YLBo7rrGVMP40uSQzGmveSPFesx-GHnxVsTah5OD9mS2j0AlNS2QYvQC-2yv-vAdB9Gl7EC6p2UbTVyoUps5hjxeYAeVgFmt2Asz8ISFhwtcUV3pOClNWilCNjEJTNIDyfDyHyBM528/s320/e.jpg

Description: https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEgBmX342xgGLiSBaApWryS2IvGHjmZpr_tIXRioYlAP5W9VM6RMJuc-QOn2bnx2-o4K3sliadjoRA6_Ams0VdOiEdgs2S-q4uGodDIDJxgj3DX9XcHlLBPaMJPurf-_NSFEan8YflNmOTra/s320/f.jpg

       PERT Chart - to elaborate but powerful tool

Time Taken In Critical & Non Critical Activities
Critical Activities
Planned Duration
Floats
Order Confirmation
1day
0
Size Breakdown receiving from the buyer
8 days
0
Bulk Fabric booking
1 day
0
Fabric In House
35 days
0
Size set ready and approval
3 days
0
PPM
1 day
0
PCD(Cutting)
1 day
0
Garment shade band submission
4 days
0
Garment shade band approval
4 days
0
Production Pull Submission
4 days
0
Production Pull approval
2 days
0
TOP Submission
6 days
0
TOP approval
4 days
0
Final Inspection
 1 day
0
X factory
1 day
0
X India
7 days
0

Non critical Activities
Planned
Float as per CPM
GSS and wash standard receiving
1 day
3 days
BOM receiving
1 day
3 days
Sampling Yardages booked
1 day
3 days
Sampling Yardages In house
2 days
3 days
FPT Report receiving from the supplier
15 days
20 days
FIT submission
7 days
8 days
FIT Approval
10 days
8 days
Wash Sample Submission
10 days
3 days
Wash sample approval
10 days
3 days
GPT Submission
7 days
18 days
YTS Submission
10 days
8 days
YTS approval
8 days
8 days
Receiving of fabric bits from the supplier
7 days
17 days
Fabric Shade band submission
11 days
9 days
Fabric shade band approval
3 days
9 days
Green tag submission
10 days
3 days
Green tag sample approval 
7 days
3 days
Trims ordered on
1 day
10 days
Trims in house
32 days
10 days
GPT Report receiving
15 days
18 days

EFFECT OF POOR MPP
Description: https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEjJEG0Lq2ofyETubDpHYdvK-W3e_MKQSp4M_t9xw_BUrn3fxb2XEVXt7MtWRWMSc7shKg2E2qQhFcK_f4M4k7LlC_4hdCK_rk8A9MulP2xJ6jygl6QyMMO1fch2vLZR2rhUHgRf3sSHVm1T/s320/c.jpg








IMPROPER PRODUCTION PLANNING
Description: https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEiNWRPJF8VHba_MpHegfR4-yANFm3-7ITzli4MKzxmnmFKzJ2KjfE_b5x536f6cFqJI1gd2f00jymn9mcnD8W_P6TlA4mdpRAkPxIq6Dkjd_GR7UVtFWNEIblurR95lMKuuNvuMED5V9ovF/s320/d.jpg

General Reasons of delay in pre-production activities
       sampling yardages
       Order of trims and fabric
       sampling threads
       wash standard achievement
       GTS sample
        Internal Miscommunication
       Concept of two buying houses
       Load in sampling and R&D Washing
       Late delivery of sampling trims and sampling yardages
       Difference between the lot of fabric used in development stage and sampling stage
       Improper handling
       Time of Issuing & stores
       Holidays & leaves
       Delay from buyer side in sending the standard  and sample
       FPT Report
       GPT report
General Reasons of delay in Production Activities
       Improper Documentation
       Start up loss
       Delay in Fabric/Trims  becoming in house
       Delay in approval of Garment shade band(as it was seen in many styles)
       Improper checking of trims at the time of in house
        Delay in approval/Review of Production Pull
       Improper quality checking
       TOP rejection or delay in approval of TOP
       Improper presentation of TOP
Merchant’s priority and critical path method
       While estimating tasks hidden safety should not be taken into account for each task .In the  case of Arvind following are the tasks where hidden safety  should not be taken:-
  • Ø  FIT Sample approval
  • Ø  Wash Sample approval
  • Ø  Production Pull submission(specially in the case of small order quantities)
  • Ø  TOP Submission.
  • Ø  Wash sample submission

.
       Early finishes should be promoted rather than completion on time   .
  • Ø   No due dates for individual tasks but finish as early as possible and hand over   , next person for next task. In the case of issuing a Sampling indent a merchant generally does not issue it to the sampling by the time sampling Yardages comes in house. In most of the cases it kills time as sampling yardages comes late .Merchant should   issue Sampling indent as soon as the order is confirmed, so that they can focus on another task.

       Lapses in the information Communication
  • Ø  . In   these cases Merchant should communicate directly face to face with the concerned person and formalities can be done in later stages. As Arvind works on Oracle data base   , so it creates such kind of problem.

       System related problem should also be removed , these problems pertain to the delay which are caused due to excess time taken in documentation, interdepartmental Communication, the release of orders, flow of work, process followed etc.
       Planning of Pre production activities
       Resubmission
       Improve resource scheduling to reduce bottle necks and improve efficiency.
  • Ø  Mostly in the case of resubmission, before the sample goes into the sampling every item should be in stock

       Un availability of sampling yardages at the time of re submission
       Actual thread and Wash sample.
       Item issue delay from the store
       Identification of Opportunities to change sequential tasks into parallel activities by understanding the true predecessor and relationships among activities.
       Creation of  proper Mechanism for communication
  • Ø  Speak clearly
  • Ø  Write clearly
  • Ø  Repeat the things
  • Ø  Get feed back from the respondent

       Criticality of wash
       Fabric/Trims In house Problem
       Imported and Local items
       Approval Problem
        Internal and external Tracking down mechanism of samples
       Proper co ordination among the team